Girder suspension of East 1st Ring (Pangjiang Street to Jianqiao Road section) succeeded on June 6
East 1st Ring Expressway is expected to be capable to open to traffic by the end of October this year
    稿源: Shenyang Daily   2018-06-06 11:16
 

From 23:00 last night to early this morning, a 130ton crane set up the first 20m long 37ton prefabricated steel-concrete composite girder at the intersection of Wanliutang Road and Lianhua Street steadily. It's been only a month since the suspension of the first prefabricated steel-concrete composite girder at the construction section of Pangjiang Street and Jinqiao Road since the beginning of May. Girder suspension at another construction section marks the construction of East 1st Ring Expressway has entered the stage of the construction of bridge superstructure. The complete date is in sight now.Truck loading, departure, transportation and hoisting. Our reporter has witnessed this historic moment.

According to the construction plan, the East 1st Ring Expressway is capable to be open to traffic by the end of October this year if construction condition permits.After the construction, the 2-way 6-lane motor vehicle lane on the bridge and the 2-way 8-lane motor vehicle lane under the bridge will improve the travel condition in the east part of Shenyang and will greatly release the traffic pressure of Qingnian Avenue and South-North Expressway.

Reporter Yu Hai

 